Upcoming Construction Projects

These projects are currently active. Watch for bidding opportunities. Be sure to register at eProcurement Exchange to participate in the bid process. It’s not too early to register!

RFP for Open-Ended Professional Design Service Contracts

IUP received 77 RFPs from Professional Design Services.  After a thorough review by the committee, 16 firms have been short-listed.  The new contracts for the Open-End RFP #01-13 will be in place by May 2014.

IN-993 Phase 1 – Crimson Café

Contracts are being awarded for the construction of a new dining café. Site work has begun, construction to be complete by Fall 2014.

Site Contract awarded to G.M. McCrossin - Bellefonte, PA

Steel Package Contract awarded to Moore & Morford - Greensburg, PA

General Construction Contract being awarded to Mid-State Construction - Altoona, PA

HVAC Contract being awarded to John Hall - Ligonier, PA

Plumbing Contract has been awarded to Vrabel Plumbing - Gibsonia, PA

Electrical Contract being awarded to Merit Electrical Group - Oakmont, PA

Food Service Equipment Contract has been awarded to 11400, Inc. - Lancaster, PA

Professional Design Firm is IKM - Pittsburgh, PA

Contracution Management Services Firm is Alvin H. Butz (Alexander) - Allentown, PA​

IN-993 Phase 2 – New Dining Facility/Renovation to Folger Hall

​This project will involve the design and construction of a new dining facility and to renovate the existing Folger Hall dining facility. Project is currently in design. We are anticipating project bidding in early 2014 with project to begin Fall 2014.

Professional Design Firm is Stantec - Pittsburgh, PA

Construction Management Services Firm is Alvin H. Butz (Alexander) - Allentown, PA​

IN-1006 Roof Replacements and Repairs

Several roofs on main campus will be repaired, with one roof being replaced. IUP Culinary building in Punxsutawney, Pa., is being replaced. Work is underway and has been contracted to Tuscano-Maher Roofing - Saltsburg, PA

IN-1010 Memorial Field House Exterior Doors/Security Study

The main entry doors and facade at Memorial Field House will be upgraded and new security to entrances througout the building will be established.

IN-1014 Stright Hall Computer Room Upgrade Study

​The study is complete. Results are being reviewed to determine project scope.

IN-1015 Zink Hall Waterproofing

Project includes installation of waterproofing panels to various exterior walls above the roof lines of the building.  The bids were due on February 4, 2014.  The bids are currently under review.  To see the list of contractors that submitted bids, please go to http://www.ebidexchange.com.  

  • Facilities Engineering and Construction
  • Robertshaw Building
    650 South Thirteenth Street
    Indiana, PA 15705
  • Phone: 724-357-2289
  • Fax: 724-357-6480
  • Office Hours
  • Monday through Friday
  • 8:00 a.m. – 12:00 p.m.
  • 1:00 p.m. – 4:30 p.m.